A hometown newspaper with a local office, local owners & lots of local news

DNR, MPCA balk on Line 3

The Minnesota Pollution Control Agency and the Minnesota Department of Natural Resources are committed to a fair, efficient, and thorough review of Enbridge’s Line 3 Replacement Project applications.

After reviewing the Minnesota Court of Appeals’ ruling regarding the Environmental Impact Statement for the Line 3 project, both agencies have determined that, consistent with state law, they may not take final action on the applications pending before them until the Public Utilities Commission addresses the EIS deficiency identified in the court’s remand.

Recognizing that state law both allows and encourages simultaneous work on environmental review and permit applications, the two agencies will continue their work reviewing the Line 3 applications. The court’s decision, however, does have implications for how this work will proceed.

The MPCA will not be releasing draft permits and the 401 water quality certification on July 1 as previously scheduled. This schedule adjustment will allow MPCA to consider the additional PUC environmental review analysis before initiating its comment process.

Once the scope and timing of the EIS revision process are established by the PUC and/or courts, the DNR and MPCA will be in a better position to determine whether additional adjustments are needed to their application review processes and timelines.

 
 
Rendered 10/16/2024 01:37